📑 Phase Summary & Strategic Overview

ORU Cloud Modernization Project

January 2026 - October 2026 | 10-Month Timeline
41
Integrations
92
Forms
498
Reports
631
Total Items
3
Mock Tests
Phase 1: Foundation & Strategic Front-Loading (Q1 2026)
Timeline:
DEC/JAN - March 2026
Deliverables:
• 18 Integrations (10 High, 5 Med, 3 Low)
• 20 Forms
• 165 Reports
Strategic Objectives:
  • Tackle 62% of high-complexity integrations early
  • Establish foundation systems and core functionality
  • Build team momentum and expertise
  • Complete Mock 3 testing (Feb 9-20)
  • De-risk project by front-loading difficult work
Phase 2: Heavy Implementation & Peak Velocity (Q2 2026)
Timeline:
April - June 2026
Deliverables:
• 14 Integrations (5 High, 5 Med, 4 Low)
• 40 Forms
• 198 Reports
Strategic Objectives:
  • Achieve peak development velocity
  • Complete remaining high-complexity integrations
  • Deliver maximum forms and reports volume
  • Execute Mock 4 testing (May 25-Jun 12)
  • Maintain balanced workload distribution
Phase 3: Final Push & Comprehensive Testing (Q3 2026)
Timeline:
July - September 2026
Deliverables:
• 8 Integrations (1 High, 4 Med, 3 Low)
• 30 Forms
• 135 Reports
Strategic Objectives:
  • Complete final 20% of integrations
  • Execute Mock 5 - Final UAT (Aug 10-Sep 4)
  • Achieve Development Complete milestone (Sept 30)
  • Validate all 41 integrations end-to-end
  • Ensure Go-Live readiness
Phase 4: Go-Live & Stabilization (Q4 2026)
Timeline:
October 2026
Milestone:
🎉 Go-Live: October 1, 2026