ORU Banner SaaS Modernization

Composition of the Remaining 20% - Root Causes, Action Plan & Key Attention Items

81%
Overall Complete
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
19%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1

Workstream Breakdown

Contribution to Remaining 20%

Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining 20%.

Area Weight Completion Remaining Contribution Key Facts
Value Stream & Capabilities
Student, HR, Finance, T&L (86% done)
86%
33% 86% 14% +4.6% Teaching & Learning 86% · HR 86% · Finance 82%
Reports
498 total - 427 done - 71 remaining
85%
19% 85% 15% +2.9% 498 go-live required · 427 done · 71 remaining
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
88%
13% 88% 12% +1.6% ISE 99% · EUP 100% · Evisions complete
Data Migration
Mock cycles, validation (70% done)
70%
9% 70% 30% +2.7% Mock 4 complete (Jun 17). Mock 5: Aug 10-21.
Integrations
42 total - 32 done - 10 remaining (76% done)
76%
7% 76% 24% +1.7% 42 required for go-live · 32 complete · 10 remain
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (32% done)
32%
14% 32% 68% +9.5% Largest single contributor - expected at this project stage. Cutover plan begins Aug-Sep.
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
100%
5% 100% 0% - Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100%
TOTAL PROJECT 100% 79.9% 20.1% = 20.1% +4.6% + +2.9% + +1.6% + +2.7% + +1.7% + +9.5% = 20.1%