ORU Banner SaaS Modernization

Composition of the Remaining --% - Root Causes, Action Plan & Key Attention Items

89%
Overall Complete
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
11%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1

Workstream Breakdown

Contribution to Remaining --%.

Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.

Area Weight Completion Remaining Contribution Key Facts
Value Stream & Capabilities
Student, HR, Finance, T&L (95% done)
95%
33% 95% 5% ~1.56% Teaching & Learning 95% · HR 95% · Finance 95%
Reports
498 total - 489 done - 9 remaining
98%
19% 98% 2% ~0.36% 498 go-live required · 489 done · 9 remaining
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
88%
13% 88% 12% ~1.48% ISE 99% · EUP 100% · Evisions complete
Data Migration
Mock cycles, validation (73% done)
73%
9% 73% 27% ~2.30% Mock 5: Aug 10-21.
Integrations
42 total - 37 done - 5 remaining (88% done)
88%
7% 88% 12% ~0.80% 42 required for go-live · 37 complete · 5 remain
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (66% done)
66%
14% 66% 34% ~4.50% Cutover planning and deployment preparation are progressing toward go-live.
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
100%
5% 100% 0% - Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100%
TOTAL PROJECT 100% 89% 11% ~11% 1.56% + 0.36% + 1.48% + 2.30% + 0.80% + 4.50% = ~ 11% (normalized to overall project remaining)