ORU Banner SaaS Modernization
Composition of the Remaining --% - Root Causes, Action Plan & Key Attention Items
87%
Overall Complete
Oct 12
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
13%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1
Workstream Breakdown
Contribution to Remaining --%.
Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.
| Area | Weight | Completion | Remaining | Contribution | Key Facts |
|---|---|---|---|---|---|
|
Value Stream & Capabilities
Student, HR, Finance, T&L (94% done)
|
33% | 94% | 6% | ~2% | Teaching & Learning 94% · HR 95% · Finance 95% |
|
Reports
498 total - 479 done - 19 remaining
|
19% | 96% | 4% | ~0.8% | 498 go-live required · 479 done · 19 remaining |
|
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
|
13% | 88% | 12% | ~1.6% | ISE 99% · EUP 100% · Evisions complete |
|
Data Migration
Mock cycles, validation (73% done)
|
9% | 73% | 27% | ~2.4% | Mock 4 complete (Jun 17). Mock 5: Aug 10-21. |
|
Integrations
42 total - 36 done - 6 remaining (86% done)
|
7% | 86% | 14% | ~1.0% | 42 required for go-live · 36 complete · 6 remain |
|
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (62% done)
|
14% | 62% | 38% | ~5.3% | Cutover planning and deployment preparation are progressing toward go-live. |
|
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
|
5% | 100% | 0% | - | Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100% |
| TOTAL PROJECT | 100% | 87% | 13% | ~13% | 2.0% + 0.8% + 1.6% + 2.4% + 1.0% + 5.3% = ~ 13% |