ORU Banner SaaS Modernization
Composition of the Remaining --% - Root Causes, Action Plan & Key Attention Items
89%
Overall Complete
Oct 12
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
11%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1
Workstream Breakdown
Contribution to Remaining --%.
Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.
| Area | Weight | Completion | Remaining | Contribution | Key Facts |
|---|---|---|---|---|---|
|
Value Stream & Capabilities
Student, HR, Finance, T&L (95% done)
|
33% | 95% | 5% | ~1.56% | Teaching & Learning 95% · HR 95% · Finance 95% |
|
Reports
498 total - 489 done - 9 remaining
|
19% | 98% | 2% | ~0.36% | 498 go-live required · 489 done · 9 remaining |
|
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
|
13% | 88% | 12% | ~1.48% | ISE 99% · EUP 100% · Evisions complete |
|
Data Migration
Mock cycles, validation (73% done)
|
9% | 73% | 27% | ~2.30% | Mock 5: Aug 10-21. |
|
Integrations
42 total - 37 done - 5 remaining (88% done)
|
7% | 88% | 12% | ~0.80% | 42 required for go-live · 37 complete · 5 remain |
|
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (66% done)
|
14% | 66% | 34% | ~4.50% | Cutover planning and deployment preparation are progressing toward go-live. |
|
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
|
5% | 100% | 0% | - | Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100% |
| TOTAL PROJECT | 100% | 89% | 11% | ~11% | 1.56% + 0.36% + 1.48% + 2.30% + 0.80% + 4.50% = ~ 11% (normalized to overall project remaining) |