ORU Banner SaaS Modernization

Composition of the Remaining --% - Root Causes, Action Plan & Key Attention Items

87%
Overall Complete
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
13%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1

Workstream Breakdown

Contribution to Remaining --%.

Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.

Area Weight Completion Remaining Contribution Key Facts
Value Stream & Capabilities
Student, HR, Finance, T&L (94% done)
94%
33% 94% 6% ~2% Teaching & Learning 94% · HR 95% · Finance 95%
Reports
498 total - 479 done - 19 remaining
96%
19% 96% 4% ~0.8% 498 go-live required · 479 done · 19 remaining
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
88%
13% 88% 12% ~1.6% ISE 99% · EUP 100% · Evisions complete
Data Migration
Mock cycles, validation (73% done)
73%
9% 73% 27% ~2.4% Mock 4 complete (Jun 17). Mock 5: Aug 10-21.
Integrations
42 total - 36 done - 6 remaining (86% done)
86%
7% 86% 14% ~1.0% 42 required for go-live · 36 complete · 6 remain
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (62% done)
62%
14% 62% 38% ~5.3% Cutover planning and deployment preparation are progressing toward go-live.
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
100%
5% 100% 0% - Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100%
TOTAL PROJECT 100% 87% 13% ~13% 2.0% + 0.8% + 1.6% + 2.4% + 1.0% + 5.3% = ~ 13%