English
Close

ORU Banner SaaS Modernization

Composition of the Remaining 18% - Root Causes, Action Plan & Key Attention Items

82%
Overall Complete
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
18%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1

Workstream Breakdown

Contribution to Remaining --%.

Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.

Area Weight Completion Remaining Contribution Key Facts
Value Stream & Capabilities
Student, HR, Finance, T&L (86% done)
86%
33% 86% 14% ~4.6% Teaching & Learning 86% · HR 88% · Finance 82%
Reports
498 total - 444 done - 54 remaining
89%
11% 89% 11% ~2.2% 498 go-live required · 444 done · 54 remaining
Platform & Products
ISE, EUP, Evisions, Experience Cards (88% done)
88%
12% 88% 12% ~1.6% ISE 99% · EUP 100% · Evisions complete
Data Migration
Mock cycles, validation (73% done)
73%
9% 73% 27% ~2.3% Mock 4 complete (Jun 17). Mock 5: Aug 10-21.
Integrations
42 total - 35 done - 7 remaining (83% done)
83%
7% 83% 17% ~1.3% 42 required for go-live · 35 complete · 7 remain
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (58% done)
58%
14% 58% 42% ~5.9% Cutover planning and deployment preparation are progressing toward go-live.
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
100%
5% 100% 0% - Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100%
TOTAL PROJECT 100% 82% 18% ~18% 4.6% + 2.2% + 1.6% + 2.3% + 1.3% + 5.9% = ~ 18%