ORU Banner SaaS Modernization
Composition of the Remaining --% - Root Causes, Action Plan & Key Attention Items
93%
Overall Complete
Oct 12
Go-Live Date
108 days
Time Remaining
72 days
Buisiness Days Remaining
7%
Work Remaining
--%
Integrations Complete
--%
Reports Complete
--%
Forms Complete
1
Workstream Breakdown
Contribution to Remaining --%.
Each row below shows one workstream: its completion rate, its estimated weight in the overall project, and its calculated contribution to the remaining --%.
| Area | Weight | Completion | Remaining | Contribution | Key Facts |
|---|---|---|---|---|---|
|
Value Stream & Capabilities
Student, HR, Finance, T&L (96% done)
|
33% | 96% | 4% | ~1.32% | Teaching & Learning 96% · HR 95% · Finance 96% |
|
Reports
498 total - 498 done - 0 remaining
|
19% | 100% | 0% | 0% | 498 go-live required · 498 done · 0 remaining |
|
Platform & Products
ISE, EUP, Evisions, Experience Cards (92% done)
|
13% | 92% | 8% | ~1.04% | ISE 99% · EUP 100% · Evisions complete |
|
Data Migration
Mock cycles, validation (88% done)
|
9% | 88% | 12% | ~1.08% | Mock 5: Aug 10-21. |
|
Integrations
42 total - 39 done - 3 remaining (93% done)
|
7% | 93% | 7% | ~0.49% | 42 required for go-live · 39 complete · 3 remain |
|
Cutover & Deploy Phases
Cutover, Business Simulation, Staging, Deploy (75% done)
|
14% | 75% | 25% | ~3.5% | Cutover planning and deployment preparation are progressing toward go-live. |
|
Complete Phases
Prepare, Plan, SAE, Environment, iPass, Extensibilities
|
5% | 100% | 0% | 0% | Prepare, Plan, SAE, Environment Readiness, iPass, Extensibilities - all 100% |
| TOTAL PROJECT | 100% | 93% | 7% | ~7% | Remaining work is normalized to align with overall project remaining. |